What happens at the end of defect liability period?
Ava Hall
Published Apr 24, 2026
At the end of the defect's liability period, the project owner will prepare a schedule of defects, listing those defects that have not yet been rectified, and agrees with the contractor on the date by which they will be rectified.
What is the meaning of defect liability period?
The defects liability period (or 'DLP') is a fixed period of time, starting from the date of practical completion, during which the contractor has an express contractual right to return to the site to rectify defects.How long is the defect correction period?
The defect correction period is also defined by in the Contract Data Part 1 as being a period in weeks (typically say 3 weeks). Under Clause 43.2, the Contractor is to correct a notified Defect before the end of the defect correction period. But, unlike the defects date this date is not necessarily tied to Completion.How long does a builder have to fix defects WA?
In Western Australia, builders are required to rectify defective works identified within six years of practical completion of the works under the Building Services (Complaint Resolution and Administration) Act 2011 (WA). This is often referred to as the statutory defect liability period.What is needed to cure the defect of the contract?
The main rationale for a right to cure is simple: fairness. If the owner thinks a supposed breach is serious enough to supplement the contractor's forces or, worse yet, terminate the agreement, then it only seems fair that the contractor should have a chance to correct the problem before the owner takes drastic action.END OF DEFECTIVE LIABILITY PERIOD (0752604866)
What does cure the defect mean?
What is a curable defect? A curable defect exists when a property has a problem that either a buyer or seller can correct based on the terms of the agreement.How does a contract become Rescissible?
A rescissible contract is one that was entered into legally by the contracting parties but has resulted in economic damage to one of the parties or an outside party. The court can therefore rescind, or set aside, the contract for equitable reasons.Can defects liability period be extended?
The Defects Liability Period for the Works shall be extended by a period equal to the period during which the Works cannot be used by reason of a defect or damage. If only part of the Works is affected the Defects Liability Period shall be extended only for that part. Extension of Defects Liability Period.Is the contractor liable for the defective work after the defects liability period?
Usually, yes. A contractor will normally remain liable for defects after the defects liability period has expired. This article addresses a common misconception about the defects liability period under a construction contract.How long are builders liable?
As per Clause 14 (3) of the Real Estate Act, a builder is liable to repair or fix any damages brought to his notice by a homebuyer within five years from the date of possession, without demanding any further charges from the homebuyer.What is an end of defects inspection?
The purpose of the end of defects inspection is to check for any remaining defects. Following the inspection the builder will arrange appointments directly with you to return and carry out final defect rectification works.What is defects liability period in building construction?
A defects liability period is the time period specified in the contract during which a contractor is legally required to return to a construction site to repair any defects which have appeared in that contractor's work since the date of construction.WHO issues last certificate on NEC contract?
Note that this certificate must be issued by the project manager within one week of the date that each sectional completion was achieved – see clause 30.2.What are the responsibilities of the client during the defects liability period of a contract?
Typically, the defects liability period is six to twelve months. During this period, the client reports any defects that arise in the works to the contract administrator who decides whether they are in fact defects (i.e. works that are not in accordance with the contract), or whether they are maintenance issues.Is defects liability period same as warranty?
Contractual Defect Liability PeriodBuilding contracts typically contain a defect liability period in respect of building works that is usually between 12 to 24 months from practical completion of the building works. In NSW, a contractual defects liability period cannot remove or limit rights to a statutory warranty.